The direct and indirect costs estimated by a contractor for bidding a project is ₹160000 and ₹20000 respectively. If the mark up applied is 10% of the bid price, the quoted price (in ₹) of the contractor is
  1. A
    200000
  2. B
    198000
  3. C
    196000
  4. D
    182000