GATE CE 2024 (S2) — Question 52

Construction MaterialsConcrete – Constituents, mix design, short-term and long-term propertiesNAT2 marksMedium

The table shows the activities and their durations and dependencies in a project.
Question image
The total duration (in days) of the project is___________ (in integer).