A water resources project with an expected life of 25 years has to be designed for an acceptable risk of 5% against a design flood. The return period for the design flood (in years) is _________________ (rounded off to the nearest integer).
GATE CE 2025 (S1) — Question 34
HydrologyHydrologic cycle, precipitation, evaporation, evapo-transpiration, watershed, infiltrationNAT1 markEasy
A GATE question every morning
One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.
More on Hydrologic cycle, precipitation, evaporation, evapo-transpiration, watershed, infiltration
- GATE CE 2026 (S2) · Q20Following statements are made with respect to the mass curve of rainfall: (I) Slope at a point on the curve can be positive. (II) Slope at…
- GATE CE 2025 (S2) · Q26In the context of the effect of drainage density on the run-off generation and the hydrograph at the catchment outlet, all other factors re…
- GATE CE 2025 (S2) · Q59The peak of flood hydrograph due to a 3-hour duration storm in a catchment is 180 m 3/s. The total rainfall depth is 6.6 cm. It can be assu…
- GATE CE 2025 (S1) · Q20To derive the total flood hydrograph at a catchment outlet from an isolated storm, the order in which the following methods are applied, fr…
- GATE CE 2025 (S1) · Q39The mean rainfall over a catchment has to be estimated. The data for four rain gauges located in and around the catchment is listed in the…
- GATE CE 2024 (S2) · Q56A storm with a recorded precipitation of 11.0 cm, as shown in the table, produced a direct run-off of 6.0 cm. The -index of this storm is c…