GATE ME 2021 (S2) — Question 18

Operations ResearchPERT and CPMMCQ1 mark · −1/3 if wrongEasy

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
  1. A
    3
  2. B
    9
  3. C
    27
  4. D
    81