The demand of a certain part is 1000 parts/year and its cost is ₹1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is ₹100/order and the lead time for receiving the orders is 5 days. If the holding cost is ₹20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).
GATE ME 2022 (S2) — Question 33
Production Planning and ControlInventory Control – deterministic models, safety stock, inventory control systemsNAT1 markMedium
A GATE question every morning
One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.
More on Inventory Control – deterministic models, safety stock, inventory control systems
- GATE ME 2026 · Q61The inventory holding cost of an item is ₹ 0.50 per unit per month and the ordering cost per order is ₹ 550. A stockist needs to supply 100…
- GATE ME 2025 · Q64A company uses 3000 units of a part annually. The units are priced as given in the table below. It costs ₹ 150 to place an order. Carrying…
- GATE ME 2024 · Q38A company orders gears in conditions identical to those considered in the economic order quantity (EOQ) model in inventory control. The ann…
- GATE ME 2023 · Q13With reference to the Economic Order Quantity (EOQ) model, which one of the options given is correct?
- GATE ME 2022 (S1) · Q22Which one of the following is NOT a form of inventory?
- GATE ME 2021 (S2) · Q46Daily production capacity of a bearing manufacturing company is 30000 bearings. The daily demand of the bearing is 15000. The holding cost…