GATE CE 2022 (S1) — Question 39

Construction MaterialsConcrete – Constituents, mix design, short-term and long-term propertiesMCQ2 marks · −2/3 if wrongEasy

The project activities are given in the following table along with the duration and dependency.
Question image
Which one of the following combinations is correct?
  1. A
    Total duration of the project = 22 days, Critical path is Q → S
  2. B
    Total duration of the project = 20 days, Critical path is Q → T
  3. C
    Total duration of the project = 22 days, Critical path is P → T
  4. D
    Total duration of the project = 20 days, Critical path is P → R
Practise the full 2022-S1 paper
Challenge a friend: WhatsApp Telegram
From RENYXERAPractise this subject in the exam simulatorTimed, GATE-style tests with analytics that find your weak topics.
Practise more on Concrete – Constituents, mix design, short-term and long-term propertiesTimed, in the real exam interface · free to start

A GATE question every morning

One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.

Join
Stuck? Ask in the student group