GATE ME 2022 (S2) — Question 41

Production Planning and ControlSchedulingMCQ2 marks · −2/3 if wrongMedium

Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is __________ hours.
Question image
  1. A
    31
  2. B
    33
  3. C
    30
  4. D
    32
Practise the full 2022-S2 paper
Challenge a friend: WhatsApp Telegram
From RENYXERAWhat rank do your marks get?GATE score, likely All-India Rank and qualifying marks for your category.
Practise more on SchedulingTimed, in the real exam interface · free to start

A GATE question every morning

One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.

Join
Stuck? Ask in the student group