GATE ME 2026 — Question 47

Production Planning and ControlSchedulingMCQ2 marks · −2/3 if wrongEasy

Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.
Question image
Which job(s) has/have critical ratio less than unity?
  1. A
    Job N and Job O
  2. B
    Job M and Job N
  3. C
    Job P
  4. D
    Job O and Job P