GATE ME 2024 — Question 34

Production Planning and ControlSchedulingMCQ1 mark · −1/3 if wrongMedium

A set of jobs \(U, V, W, X, Y, Z\) arrive at time \(t = 0\) to a production line consisting of two workstations in series. Each job must be processed by both workstations in sequence (i.e., the first followed by the second). The process times (in minutes) for each job on each workstation in the production line are given below.
Question image
The sequence in which the jobs must be processed by the production line if the total makespan of production is to be minimized is
  1. A
    \(W\)-\(X\)-\(Z\)-\(V\)-\(Y\)-\(U\)
  2. B
    \(W\)-\(X\)-\(V\)-\(Z\)-\(Y\)-\(U\)
  3. C
    \(W\)-\(U\)-\(Z\)-\(V\)-\(Y\)-\(X\)
  4. D
    \(U\)-\(Y\)-\(V\)-\(Z\)-\(X\)-\(W\)
Practise the full 2024 paper
Challenge a friend: WhatsApp Telegram
From RENYXERAThis week's 10-question challengeSame 10 past-GATE questions for everyone this week — see where you stand.
Practise more on SchedulingTimed, in the real exam interface · free to start

A GATE question every morning

One real past-paper question every morning for your branch, answer hidden until you tap. Free on Telegram.

Join
Stuck? Ask in the student group